Solar Power Project
113 Solar Panels
5 Batteries
Load Management System
Benefits:
Lower energy bills free up money to support Outreach and other initiatives.
Promotes environmental stewardship
Want to support the project?
Make a donation and note “solar”
Make a pledge by emailing treasurer@upcelp.org
Questions? See Mike Halpin, Debra Little or Jerry Hobson
Timing:
July 2026 – Contract signed, initial supplier payment, and work started
Late-2026 Solar panels installed and operational
Mid-2027 Federal credits for panels
Mid-2027 Battery system installed
Mid-2028 Federal credits for battery system
Financials:
Cost: $113,116 ($226,232 less a 50% federal credit)
Payback: 7 to 9 years depending on future electricity cost and federal credit assumptions
Funding goal: $115,000 in member donations to cover system cost
Donations Received - $67,500
Pledges - $7,000
Additional Donations Needed - $40,500
Bridge Loan: $99,000 to cover period between supplier payment and receipt of federal credits. Application is presently being filled out at UPC.